Phase One – The Pilot Phase

(January 1, 2007 – May 1, 2007)

December 2006 Hire the Project Manager.
January 2007 Complete funding and research agreements.
February 2007 Finalize research team
February 2007 Finalize the MMR Operational and Research Design and obtain Institutional Review Board approval.
January – March 2007 Determine reporting needs including: frequency, content, and audience. Define dashboard of metrics for traffic monitoring over the 18-month study.
March 2007 Finalize vendor selection for traffic monitoring, both for perimeter and selected segments inside the network.
March 2007 Conduct an initial goals-directed behaviors campus-wide survey.
March 2007 Conduct initial focus groups of students.
April 2007 Pilot test network traffic monitoring capabilities and implement the final monitoring configuration.
April 2007 Establish a clear baseline set of traffic data before the end of the spring semester.
May 2007 (ongoing) Establish data collection and distribution plan, including guidelines for protecting the privacy of participants.
May 2007 Hire support staff, including full-time network engineer and research assistant.

 

Phase Two – Baseline Data & Social Science Gathering

(May 1, 2007 - December 15, 2007)

May – August 2007 Use summer to debug live network.
June – July 2007 In-depth Interviews of 30 students using Mental Models approach.
June – July 2007 Survey Preview 2007 participants.
August 2007 Refine network data elements to be collected during fall 2007.
August 2007 All equipment should be installed and tested for September data collection.
August 2007 Analyze and report out on Phase One baseline network data.
August 2007 Apply for next round of funding/grants.
August 2007 Analyze and report out on Phase One Behavioral data.
August – September 2007 Network Data Collection.
November 2007 Prepare for implementation of legal media services in Phase Three, including identification of services and negotiations with service providers.
November 2007 Plan logistics, staffing, etc. for going live with escalated response.
November 2007 Create birdtrax Web site. – legal media services
November 2007 Develop and test educational module capabilities. Test and be ready for implementation with escalated response.

 

Phase Three – Implementation of Legal Services/Escalated Response  

(December 15, 2007 – June 30, 2008)

December – June 2008 Analyze and report out on Phase Two and Phase Three data before June 30.
December – June 2008 Continue to collect network data and analysis.
January 2008 Activate legal media services, promote registration.
January 2008 Go live with escalated response program and education modules.
January – May 2008 Monitor response of students to legal media services.
January – May 2008 Monitor response of students to escalated response system.
January – May 2008 Respond to encryption counter-measure.
May 2008 Identify Illinois State policies for discussion and reconsideration.
May 2008 Identify industry issues for discussion.
May 2008 Consider not sponsoring university-subsidized legal media services, but using only pass-through options.
June 2008 Introduce birdtrax to Preview students/parents and register new users in June/July 2008.
June 2008 Submit articles and reports for publication/presentations.
August 2008 Focus attention on P2P issues, ISU environment, birdtrax opportunities at Passages (new student orientation) in August 2008 for all new students.